Replacement of Structure No. 25-WG, Atkinson’s Bridge, Jones Baseline at Irvine Creek (former Townships of Nichol and West Garafraxa) in the Township of Centre Wellington

PROJECT DESCRIPTION

The work comprised of the demolition and replacement of the single-span, concrete, bowstring-arch bridge structure containing abutments in Irvine Creek and the planning, design and construction of a new 33.0m x 9.7m CPCI 1600, two-lane Single Span Integral Abutment Bridge in accordance with a Schedule “B” Environmental Assessment.

Triton’s services for this project:

  • Approvals and reports including Archaeological and Heritage Impact Assessment (HIA), Ministry of the Environment and Climate Change (MOECC) and Grand River Conservation Authority (GRCA)
  • The demolition and removal of existing concrete structure
  • Construction of a new 33.0m x 9.7m CPCI 1600 single span integral abutment concrete structure
  • The new structure consisted of concrete abutments, integrated pre-cast concrete girders and reinforced concrete deck complete with concrete barriers, guiderails and asphalt pavement
  • Realignment and road base widening of Jones Baseline on both approaches to accommodate the widened bridge structure
  • The project was constructed in 2011 at a cost of $1,500,000