Completion of a Schedule B Class Environmental Assessment to convert the facility from a secondary to a tertiary treatment plant without a change in treatment capacity
Recommended solution included new influent works, rehabilitation of primary clarifiers, conversion of aeration system to fine bubble from mechanical aeration including the addition of a third aeration tank, rehabilitation of existing secondary clarifiers including the addition of a third clarifier, tertiary filtration, UV disinfection, conversion of anaerobic digesters to aerobic digesters and new biosolids storage facilities.
Project was completed in three phases to lessen the impact on the Town’s annual budget
Completed final design and construction contract administration
Secured funding from federal and provincial governments